Hundung Substation Transformer under Replacement; Power Disruption in Phalang Feeder Areas

Must Read

Online Registration is Mandatory

Ukhrul, June 4: Manipur State Power Company Limited on Wednesday informed that the 1MVA power transformer at 33/11KV substation, Hundung tripped on June 2, 2025, and rectification works have not yielded results.

A press note issued by MSPCL said, “to get the substation operational as soon as possible, the substation will remain in shutdown for a few days for replacement of the faulty 1MVA power transformer.”

Also read | One Life Lost, Thousands Displaced: Manipur’s Flood Toll Grows

Further, the MSPCL, Substation at Khumanlampak, Imphal while regretted the power supply disruption, and the inconvenience caused to the public, added that all areas serviced by 11KV Phalang feeder will be affected during the aforementioned period.

- Advertisement -

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Latest News

KKAA Elects Nongmaithem Sekendro as President for Three-Year Term

IMPHAL/UKHRUL: The Khundrakpam Kendra Artists’ Association (KKAA) has elected Nongmaithem Sekendro as its new president for a three-year term.The...
Online Registration is Mandatory
- Advertisement -

More Articles Like This

- Advertisement -